National Appeals Chamber

Tales from the National Appeal Chamber: Non-statutory grounds for in-house procurement?

Municipal waste collection and transport is the subject of many in-house procurements in Poland. Art. 67(1)(12) of the Public Procurement Law provides one of the possible grounds for awarding such contracts, requiring the contracting authority to meet three conditions. But are there really only three? This issue arose in a case in which the National Appeal Chamber had to decide whether the contracting authority must also meet other, non-statutory conditions to properly award a sole-source contract.

Tales from the National Appeal Chamber: A contractor may freely allocate the value of individual parts of a lump-sum fee

When valuing bids in a public procurement procedure as a lump sum, contractors may freely determine the value of individual parts of the contract. For the contracting authority, only the total value of the contract is relevant, and not the valuations of individual parts. But in every case the contractor should examine the documentation to determine whether the contracting authority has included any limitations in this respect. This is the guidance that can be drawn from the ruling by the National Appeal Chamber of 20 October 2020 (KIO 2101/20).

Tales from the National Appeal Chamber: The contracting authority must create equal conditions for all contractors

Fair competition and equal treatment of contractors are the main principles of awarding public contracts, and all actions taken by the contracting authority in preparing and conducting the procedure must comply with these principles. Nonetheless, procurement procedures often raise questions about how these principles should be applied in practice. Some doubts were recently dispelled by the National Appeal Chamber in its ruling of 15 October 2020 (case no. KIO 2104/20).

Tales from the National Appeal Chamber: Proper calculation of the three-year exclusion period for breach of an earlier contract

An optional ground for exclusion from procurement proceedings, breach of an earlier public contract, is limited to three years after occurrence of the event that is basis for the exclusion. But a problem arising in practice is which event should be considered when calculating the three-year period. Termination of the contract by the contractor? Repudiation of the contract by the contracting authority? Or perhaps entry of a judgment for damages for breach of the earlier contract? The answer can be found in the ruling by the National Appeal Chamber of 26 August 2020 (case no. KIO 1781/20).

May a contractor whose offer is rejected appeal to the National Appeal Chamber?

A contractor filing an appeal must duly demonstrate that it has standing to appeal under Art. 179(1) of the Polish Public Procurement Law. There is an endless debate in the case law and the legal literature over which entities are entitled to file an appeal in a procedure for award of a public contract. The National Appeal Chamber spoke out in this dispute in its ruling of 23 October 2019 (case no. KIO 2031/19), responding to the question whether a contractor whose bid has been rejected still has a legal interest in filing an appeal.

Tales from the National Appeal Chamber: Consequences of imprecise description of conditions for participation in contract award procedure

In the tender documentation, the contracting authority may require contractors to meet certain conditions for participation. These should be precise and duly described so the contractors can adequately demonstrate their fulfilment. But what if the contracting authority has not precisely defined a condition for participation in the procedure? In its ruling of 3 July 2020 (KIO 1001/20), the National Appeal Chamber held that the interpretation of the condition more favourable to the contractor should be applied.